Another garage build
Posted
Old Timer
More progress, roof materials arrived today and laid some more bricks.
Posted
Moderator
Posted
Old Timer
borednow said
Nice!, You'll be finished soon at this rate
Ian
I'm hoping to get the roof on over Christmas. Hopefully by the end of next week should be getting to roof height.
I have all the safety bits and thick plastic to remove the existing asbestos sheet roof. Then need to knock through to the existing garage and change the levels so the back wall is not sloping down.
Rubber roof and fitting kit came and have a new lintel for the main garage door. Going to replace the up over door with an insulated roller jobbie
Posted
Old Timer
This mornings progress:
Posted
Old Timer
Progress today:
Posted
Old Timer
You'll have the roof on and be using it as Santa's Grotto by Sunday!
Posted
Old Timer
TBigJohn said
You'll have the roof on and be using it as Santa's Grotto by Sunday!
Posted
Old Timer
A few more courses done and corner built up for tomorrow, built the frame for the window so should have that set up as well.
Posted
Old Timer
Busy this morning
Posted
Old Timer
Built up the corner to final height more tomorrow
Posted
Old Timer
Posted
Moderator
Posted
Old Timer
Side wall up to final height. Just have the blocks to finish off for piers.
This weekend should get the remaining walls done with lintels :D
This weekend should get the remaining walls done with lintels :D
Posted
Old Timer
Managed to get the back wall up this morning before the heavy down pours. The weather has been a bit hit and miss the last few weeks. Next week should see the lintels put up for the door and window and completion of that section. Bricks are starting to run low but enough to complete the new section and hopefully enough for the original garage.
The plan between Christmas and new year is to get the wall plates on, joist hangers, joists and OSB board on the new section of the garage. Knock through the wall to join old and new and then put all my gear and the Golf in the new section.
Then if we have any spare time and the weather is kind take the old roof down and start to build up the levels to match the new bit. I have a new lintel for the main garage door as the old one looks a bit dodgy Anyway pics of work:
The plan between Christmas and new year is to get the wall plates on, joist hangers, joists and OSB board on the new section of the garage. Knock through the wall to join old and new and then put all my gear and the Golf in the new section.
Then if we have any spare time and the weather is kind take the old roof down and start to build up the levels to match the new bit. I have a new lintel for the main garage door as the old one looks a bit dodgy Anyway pics of work:
Posted
Moderator
Posted
Old Timer
borednow said
Looking good mate
Not jealous at all
Ian
Cheers chap, getting there now.
Posted
Old Timer
bit more progress today:
Posted
Old Timer
Ready for final couple of courses tomorrow, wall plates on at the weekend
Posted
Old Timer
You're not hanging around on this are you?
Posted
Old Timer
TBigJohn said
You're not hanging around on this are you?
Need to finish my Golf and get it back on the road for the summer is the drive